HEATHROW T2 OPERATIONAL READINESS
Overview
Heathrow Airport was due to open its new Terminal 2 in June 2014. In order to achieve a smooth opening on day 1, Heathrow engaged us for its Operational Readiness and Testing programme. Heathrow needed to resource this programme quickly with competent interim staff that could deliver a gruelling terminal testing programme.
Solution
13 interim staff: we provided 13 of our associates to the T2 Operational Readiness Program all with high level process and people skills.
FF&E: our staff designed and ran the entire logistics process to deliver 33,000 items of fixtures, fittings & equipment to the terminal.
Airbridge testing: our staff defined a new approach to air-bridge calibration & testing which has now become the UK standard for such trials.
Outcome
A successful opening was achieved with no adverse press coverage.
We enabled the safe and successful delivery of 190 proving trials with over 14 000 trial participants.
We delivered 65 airside proving trials including live aircraft tests.
We delivered a seamless logistics function providing 33,000 items to the terminal.